An
Analysis
of Alternative Tariff Systems for Taiwan
An
abstract from an extensive
study
commissioned
by Taiwan Power
Company
The
UPLAN
modeling system is
used to simulate the Taiwan power system in order to compare
alternative grid
pricing and tariff methods.
The
crucial
features critical to the Tariff Analysis are UPLAN’s ability
to simulate a wide range of
scenarios regarding restructuring, market design, market uncertainties,
and
business and investment strategies. The key models are the Volatility
Model and
the Merchant Plant Model that are linked to (and rely on outputs from)
the OPF
and Multi-Market models. The model uses a specially developed database
that
captures the technical parameters of generator and transmission
elements that
constitute the Taiwan network. Also factored in are financial data on
these
assets, as well as uncertain market drivers such as fuel prices, load
growth
and hydro conditions.
The
principal UPLAN reports
used for the analyses (2002 through 2006):
- power
flows on different grid elements;
- hourly
grid-wide and location-specific electricity prices (or marginal costs),
transmission constraints (congestion) and costs for resolving
constraints;
- projected
system thermal losses and related costs;
- hourly
prices and costs for certain ancillary services based on simulated
generator
bidding with arbitrage among the different markets; and
- financially
rational generator additions (not announced) for longer-term
simulations to
evaluate potential stranded costs for existing generators.
Grid
access charges
Embedded
Costs - Five
different methods were used to determine tariffs to recover embedded
transmission ownership costs. Case 1 applies
grid-wide $/MWh postage
stamp charge to loads based on their MWh of load, and grid
administration costs
are recovered by a second $/MWh charge to loads (also in case 3). Case
2 uses
a $/kW “license plate” charge to loads in each of
four zones based on annual
peak kW of load. Grid administration costs recovered on a system-wide
basis. In
Case 3, recover 50% from loads on a system-wide
basis, based on average
monthly peak load over the four summer months June-September, the other
50% of
transmission ownership costs are recovered from generators based on
their kW of
capacity. In Case 4 a “line
usage” method., based on the change in power
flow over the element calculated to be caused by the particular user,
divided
by the overall power flow on that element due to the particular user
plus all
other users combined. “Users” are defined as
seller-buyer (generator-load)
combinations, rather than as loads alone. Four alternative methods are
used to
calculate power flow changes: modulus (absolute flow change), zero
counterflow,
dominant flow, and net flow. Case 5. Like Case 4,
except that (1)
“users” are defined in terms of load location and
magnitude but not as specific
seller-buyer (generator-load) combinations, (2) a particular
user’s fractional
share of a given grid element’s cost is calculated as the
user’s marginal
impact on power flows over that element, and (3) power flow impacts are
calculated using shift factors. Grid administration charges are the
same as in
Cases 2 and 4 and 5.
Grid
Administration Cost Recovery - These are assumed recoverable on a
grid-wide
(not zonal) basis, using a per-MWh or per-peak kW postage stamp charge.
Total
“Access” Charges - A user’s total
“access” charge includes the charges to
recover costs of transmission and distribution ownership plus grid
administration.
In
summary,
“Access Tariff” Cases 1 through 3 use
straightforward license plate allocation
of transmission ownership costs and give the most uniform and
predictable
overall rates. The zonal transmission charges in Case 2 may send
desirable
signals regarding zonal costs, but may also excessively penalize users
in zones
with transmission assets that substantially benefit users in other
zones. Cases
4 and 5 use line usage methods to allocate transmission ownership
costs,
resulting in highly varied charge rates among users. Because it is
based on
load locations rather than generator-load combinations, the line usage
method
used in Case 5 is more computationally feasible than the method used in
Case 4,
produces charge rates that are somewhat more uniform and predictable,
and is
guaranteed to produce charges that sum to exactly 100% of costs being
allocated.
Congestion
Costs
Under
projected “most likely” conditions for 2002-2006,
no congestion (constraints on
transmission interfaces) was simulated to occur for the Taiwan grid.
Several likely conditions have been examined. For purposes of
illustrating
congestion costs and charges, a scenario was constructed based on
projected
year 2002 conditions, but with two nuclear units and one fossil unit in
the
northern zone (zone 1) assumed to be on outage during the peak load
months of
July and August. Combined with the double (two-line) transmission
outage
contingency incorporated into the simulated total transfer capacity
(TTC) for
transmission links between the different zones, this represents a very
low
probability combination of unfavorable circumstances.
The
first of
three methods illustrated for charging users for congestion is based on
zonal
electricity prices. Under the simulated congestion scenario, zonal
electricity
prices were the same across the different zones during 1,412
July/August hours,
but in the remaining 76 hours the zonal prices were substantially
higher in the
northern zone (zone 1) due to transmission constraints that created a
need to
re-dispatch higher cost generation in that zone. Two alternative
approaches to
allocating congestion costs without use of zonal electricity prices are
simply
to divide the cost of generator re-dispatch among (1) all users (loads)
system-wide or (2) all users in the load pocket zone. Typically, these
re-dispatch costs would be allocated on a pro rata “postage
stamp” basis, in
proportion to each user’s MW of load in an hour in which
constraints and
re-dispatch occur.
Losses
Hourly
transmission losses were projected based on AC power flow simulations
taking
into account the electric properties of the grid, generator dispatch,
and
hourly consumption at the numerous load buses. Typically, losses costs
would be
included in grid users’ hourly electricity prices. This
billing might be based
on general loss factors periodically calculated for a limited number of
different grid conditions, using power flow simulations. Then, when
final
accounting shows that actual hour by hour losses were somewhat
different than
this, there will be billing adjustments. Bilateral transactions may be
given the
option of making up losses in kind, via increased generation.
Ancillary Services
Ancillary
services (AS) considered in the study are regulation up, regulation
down,
spinning reserve and non-spinning reserve. These services were
simulated
2002-2006 through marginal cost-based methods. AS costs were
also calculated
using an “average cost” method. For illustration,
costs of these four AS under
market-based and cost-based pricing as allocated on a postage stamp
basis. Two
other generator-based AS, reactive supply (voltage regulation) and
black start,
depend on particular generator characteristics and locations, so that
their
costs are not well represented by simulating hourly markets for these
AS.
Stranded costs
Generators
owned by an incumbent utility may experience reduced operating incomes
due to
decline in market share and/or prices in newly deregulated markets with
open
transmission access. These investment costs are unrecoverable, or
“stranded.”
Two basic methods for calculating stranded costs are as follows.
- A
generator’s net operating
income can be compared to the income level needed to recoup the
investment cost
(depreciation plus return). If the income level falls short, there are
stranded
costs.
- A
generator’s net operating
income after some precipitating event (such as deregulation
or loss of a
customer) can be compared to the net operating income in the absence of
the
event. The difference represents stranded costs caused by the event,
and
stranded costs calculated in this manner may be quite different from
those
calculated under the first approach.
To
estimate
the reduced net income projected for existing Taiwan Power generators,
two
UPLAN scenarios were tested for horizons from 2006 through 2025: (1)
assuming
that all generators run and sell power based on bids indicative of
their
marginal costs, and (2) alternatively assuming that output from certain
IPP
generators must be taken under existing arrangements (“IPP
must-take”). The
“must-take” scenario results in a projected NPV of
net income for existing
Taiwan Power generators is shown to be 43% lower, due to a combination
of lost
market share and lower prices. The report identifies specific
generators that
potentially suffer stranded costs.